Construction Progress - July 2007
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
|
|
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

The living room of A5 is now fully painted and tiled.
|

The tiling of A5's front veranda is also complete.
|

Next
our crew will begin installing woodworks in A5, starting
with the teak molding that will frame the windows and doors.
|

Here
is a view of the enormous wrap
around veranda of beachfront condo A5.
|