Construction Progress - August 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
Sept
07 |
Sept
07 |
Oct
07 |
Nov
07 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

A5 is painted and tiled and woodworks are presently being installed.
|

Here is where the kitchen cabinets of A5 will soon be installed.
|

All
of the teak window and door molding has been installed.
|

The
guest bedroom closets of A5 will soon be installed.
|

The
painting of the veranda of A5 is now
complete. Next, handrails will be installed.
|

Here is one of the many gorgeous Caribbean views from A5.
|

The
master bedroom closets will soon be installed.
|

Soon
the entirety of Building A will be finished in acrocrete