A5 Construction Progress - September 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

X

X

X

Oct 07

Oct 07

Oct 07

Nov 07

% Complete

70%

75%

80%

85%

90%

95%

100%

The Phoenix Resort in Belize Condo A5 #1



The kitchen cabinets are presently being finished in condo A5.



The Phoenix Resort in Belize Condo A5 #2



Many other woodworks are also being installed throughout A5.






The Phoenix Resort in Belize Condo A5 #3




A5 offers spectacular Caribbean views from inside and on its veranda.





The Phoenix Resort in Belize Condo A5 #4




Here is the enormous wrap around veranda of condo A5.






The Phoenix Resort in Belize Condo A5 #5



A5 is the second floor condo seen here. Above, on A9's exterior wall, can
be seen a crew member preparing for the installation of the pergolas.






The Phoenix Resort in Belize Condo A5 #6



After the pergolas have been installed
the handrails of Building A will follow.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6


The Phoenix Property 1




Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery