A5
Construction Progress - September 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
Oct
07 |
Oct
07 |
Oct
07 |
Nov
07 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

The kitchen cabinets are presently being finished in condo A5.
|

Many other woodworks are also being installed throughout A5.
|

A5 offers spectacular Caribbean views from inside and on its veranda.
|

Here is the enormous wrap around veranda of condo A5.
|

A5
is the second floor condo seen here. Above, on A9's exterior wall,
can
be seen a crew member preparing for the installation of the pergolas.
|

After
the pergolas have been installed
the handrails of Building A will follow.
|