Construction Progress - October 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
X |
Nov
07 |
Nov
07 |
Nov
07 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

Here
is a view of A5's spacious wrap around veranda.
|

The
finish work in A5 is now complete and the
condo's GE stainless steel appliances are now onsite.
|

This
is the recently built kitchen island of A5.
Soon its granite countertops will be installed.
|

The
Jacuzzi in A5's master bathroom was recently installed.
|

The toilet and cabinets in A5's master bathroom have been installed.
Next our crew will install the marble countertops and Kohler fixtures.
|

The
shower fixtures in A5's master bath have also been installed.
|

This is the gorgeous Caribbean view from A5's veranda.
|

Here
is the view of the site of the main
pool of The Phoenix from A5's veranda.
|