A4
Construction Progress - May 2007
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
|
|
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

Our construction crew recently finish plastering this back hallway.
|

A4 is the condo pictured here and offers 1,500
interior square feet and 550 veranda square feet.
|

This
is the western face of Building A. Soon it will be smooth
plastered, and then covered in a cream colored acrocrete.
|

The outer walls of A4 will also soon be coated in acrocrete.
|