A4 Construction Progress - August 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

X

Dec 07

Dec 07

Jan 08

Feb 08

Mar 08

Apr 08

% Complete

70%

75%

80%

85%

90%

95%

100%


The Phoenix Resort in Belize Condo A4 #1


The exterior walls of A4 are now being painted with acrocrete.




The Phoenix Resort in Belize Condo A4 #2


A4 is presently being used to store construction equipment.
Here's an overhead perspective of its spacious veranda.