Construction Progress - May 2008
| Milestone |
Paint & Tile |
Kitchen
&
BTH Cabinets |
Appliances
& Fixtures |
Wood
Finish Work |
Furniture |
Complete |
|
Completion Date |
X |
X |
June
2008 |
June
2008 |
June
2008 |
June
2008 |
| %
Complete |
75% |
80% |
85% |
90% |
95% |
100% |
|

Here
is the private 550 square foot veranda of condo A4.
|

This is the Caribbean view from condo A4 looking
out over the lap pool and main pool of The Phoenix.
|

Both
the master and guest bathrooms have been
largely completed and fixtures have begun being installed.
|

A4
is the first floor two bedroom condo seen here. The living
room, guest bedroom, and master bedroom all open onto the veranda.
|