A3 Construction Progress - July 2007


Milestone

Foundation

Walls

Roof

Windows & Doors

Paint & Tile

Finish Work

Complete

Completion Date

X

X

X

X

X

 

% Complete

20%

40%

60%

70%

80%

90%

100%

The Phoenix Resort in Belize Condo A3 #1



The kitchen cabinetry is now being installed in A3.


The Phoenix Resort in Belize Condo A3 #2


A3's veranda extends 12' towards the pool and
grounds and offers 550 square feet of space to relax on.



The Phoenix Resort in Belize Condo A3 #3




Here is the Caribbean view from A3's veranda.



The Phoenix Resort in Belize Condo A3#4



A3 is the first floor condo seen here. Its veranda was
recently tiled and its exterior is in the process of being painted.