A2
Construction Progress - December 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
Jan
08 |
Jan
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

Here
is the east half of Building A in late December
2007. A2 is the first floor condo seen here on the right.
|

Our
crew has started to raise the elevation of the ground around
A2's veranda.
Finished ground level will be one step down from A2.
|

Here
is the living room and
kitchen of condo A2 in December 2007.
|

Many
of the GE stainless steel appliances and all
of the granite countertops were installed this month.
|

The
countertops are made from granite mined in Guatemala.
|

The
kitchen island has a separate
breakfast bar installed at table height.
|

The
guest bathroom's marble countertop was recently
installed. The sink was offset to create an area to fold laundry.
|

The
master bathroom's marble countertop and
Kohler fixtures were also recently installed.
|

The
Jacuzzi tub's marble trim was also installed in December 2007.
|

Large
benches were built into the back
wall of each shower to make bathing easier.
|

The
veranda of condo A2 will offer sun
in the morning and shade in the afternoon.
|

Here
is the Caribbean view from A2's
veranda overlooking ongoing pool construction.
|