A1
Construction Progress - July 2007
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
X |
|
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

Here is the recently installed kitchen cabinetry of condo A1.
|

The fans and light fixtures were also recently installed in A1.
|

Teak
molding frames all of the windows and doors.
|

The
walk-in closet in the master
bedroom offers owner's storage above.
|

Here is the master bathroom cabinetry.
|

A1 offers an enormous wrap around veranda.
|

The
exterior surface of Building A is presently being painted.
|

With all of the verandas tiled along Building A
our crew will soon paint the faces of each veranda.
|