Construction Progress - August 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
X |
Sept
07 |
Oct
07 |
Oct
07 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

The
application of the cream colored
acrocrete to Building A is nearly complete.
|

Here are the kitchen cabinets inside condo A1.
|

The
woodworks in A1 are complete
and furniture is now being delivered.
|

All
of the interior doors have been installed in A1.
|

In the master bedroom furniture has started to arrive.
|

There
is furniture in the guest bedroom of A1 as well.
Next,
plumbing fixtures, countertops, and appliances will be installed.
|