A1
Construction Progress - December 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
Jan
08 |
Jan
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

Here
is the east half of Building A in late December 2007.
A1 is the first floor condo on the east corner of Building A.
|

Our
crew has started to raise the elevation of the ground around
A1's veranda.
Finished ground level will be one step down from A1.
|

The
spacious kitchen of condo A1 was recently completed.
|

The
GE stainless steel appliances and
granite countertops were installed in December.
|

The
countertops are made from granite mined in Guatemala.
|

The
kitchen island has a separate
breakfast bar installed at table height.
|

The
guest bathroom's marble countertop was recently
installed. The sink was offset to create an area to fold laundry.
|

The
master bathroom's marble countertop and
Kohler fixtures were also recently installed.
|

The
Jacuzzi tub's marble trim was also installed in December 2007.
|

Here
is one of the many beautiful
Caribbean views from A1's veranda.
|