A11 Construction Progress - August 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

X

X

Aug 07

Jan 08

Feb 08

Mar 08

Apr 08

% Complete

70%

75%

80%

85%

90%

95%

100%

The Phoenix Resort in Belize Condo A11 #1



Here is the amazing Caribbean view from A11's veranda.


The Phoenix Resort in Belize Condo A11 #2


The veranda of A11 has been tiled. The
application of acrocrete will soon be complete.








The Phoenix Resort in Belize Condo A11 #3



Here is the living room and kitchen of A11. The room
has been tiled and grout is presently being applied.







The Phoenix Resort in Belize Condo A11 #4




Here is the guest bedroom of A11 being tiled in early August 2007.





The Phoenix Resort in Belize Condo A11 #5




Here is the master bedroom of A11 being tiled in early August 2007.





The Phoenix Resort in Belize Condo A11 #6



Here is a view of A11's veranda prior to the application of acrocrete.



A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6



Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery