A11
Construction Progress - May 2008
| Milestone |
Paint & Tile |
Kitchen
&
BTH Cabinets |
Appliances
& Fixtures |
Wood
Finish Work |
Furniture |
Complete |
|
Completion Date |
X |
X |
May
2008 |
May
2008 |
May
2008 |
May
2008 |
| %
Complete |
75% |
80% |
85% |
90% |
95% |
100% |
|

The
kitchen of condo A11 will be completed later this month.
|

The
granite countertops and GE stainless steel
appliances
will be installed in A11 this week.
|

All
of the teak molding around the windows and doors
and the curtain rods have been installed in condo A11.
|

Here
is the Jacuzzi tub of condo
A11 prior to marble being installed.
|

The
marble countertops in the guest
bathroom will be installed this week as well.
|

Here is the spacious private veranda of third floor condo A11.
|

Condo
A11 looks out onto the lap pool of The Phoenix.
|

Here
is a view of the main pool of The Phoenix
and the Caribbean beyond from condo A11.
|