Construction Progress - August 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
Oct
07 |
Nov
07 |
Nov
07 |
Dec
07 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

In this picture looking out through A10's living room
windows protective plastic can be seen taped up on the veranda.
|

A10's
living room and kitchen has been painted
and tiled. Woodworks will be installed later this year.
|

This
view looks out through the painted and tiled guest bedroom.
|

Here is the master closet found in the master bedroom of A10.
|

The
showers of A10 are almost complete and will soon be tiled.
|

Here is a view of A10's veranda during the application of acrocrete.
|

A10 offers a long main hallway where the
condo's interior doors will soon be installed.
|

Here is the spectacular Caribbean view from the veranda of A10.
|